Delivery condition is the state the premises must be in when the landlord hands over possession: the shell or finish level, which building systems work, whether the space is code-compliant, and what landlord work is done. “As-is” is the shortest possible answer to that question and the one tenants misread most often — it removes the landlord’s obligations rather than describing the space, so on its own it guarantees nothing except that the landlord will not be improving what it delivers.

One event, four questions

A delivery provision looks like a single sentence and is really four separate answers. When must the landlord hand over possession, and on how much notice? In what physical condition? What has the landlord agreed to build, and what counts as done? And what happens to the tenant’s money and the tenant’s schedule if the answer arrives late?

Each answer sits in a different place in the document, which is why delivery disputes are so often a scavenger hunt. The date may be in the basic lease information, the condition in an exhibit, the landlord’s work in a work letter, the completion standard in a definition of substantial completion, and the remedies in a section titled something like “delivery; delay” that few people read because it is short and sounds administrative. The tenant’s build-out schedule, its cash flow and its holdover exposure at the old space all hang off how those five pieces line up.

The practical way to read delivery is to ask who bears each risk. Who bears the risk of the space not being ready? Who bears the risk that the space is not legal to occupy? Who bears the risk that the space does not fit the tenant’s use? A well-negotiated lease answers all three explicitly. The landlord’s standard form answers the first two in its own favour and leaves the third to silence.

The label is not a specification

The industry runs a vocabulary of delivery labels, and the vocabulary is not standardised. Cold dark shell — sometimes cold shell, dark shell or bare shell — is structure, envelope and roof with service points at the edge and nothing distributed inside. Grey shell sits somewhere above that with some systems roughed in, though a great many brokers use “grey shell” to mean the barest cold shell. Warm shell usually means a working HVAC unit and electrical service, and sometimes a restroom. White box and vanilla box describe a space with distributed core systems and basic finishes: primed demising walls, a ceiling grid, lighting, HVAC distribution, branch circuits, a code-compliant restroom. Turnkey means the landlord builds to an agreed plan and hands over a finished space. Second-generation space is whatever the last tenant left behind, which can be the cheapest or the most expensive starting point in the building.

The American Bar Association’s Probate & Property has made the point plainly: these construction terms have no fixed definitions and vary by region, municipality and company. Two leases can both say “warm shell” and mean, on the same facts, a ducted and commissioned system in one and a rooftop unit with no duct, no thermostat and no gas line in the other. Both landlords will tell you they delivered a warm shell, and both will be telling the truth about their own definition.

That is why the label belongs at the top of an exhibit that then itemises the inclusions and exclusions line by line: electrical service amperage and panel capacity, HVAC tonnage and how far the distribution runs, plumbing rough-in and fixture count, sprinkler configuration and whether it is a shell-and-core main or a full grid, slab tolerance, ceiling height and whether a ceiling exists at all, demising wall finish, restroom condition, and where utilities enter the suite. Anything not on the list is the tenant’s cost. A restaurant should add grease interceptor location, gas service size and roof access for hoods; a dental or medical tenant should add the plumbing and electrical capacity its equipment actually draws; a lab should add exhaust and make-up air.

“As-is” is the last label on the spectrum and the only one that is not really a description at all. It does not say the space is any particular thing. It says the landlord is making no promise that it is anything — no work, no warranty, no suitability for the tenant’s use. Everything the tenant needs beyond the four walls and the existing systems is the tenant’s project.

Three dates that decide who pays for a slip

A delivery clause that names one date has named the least useful one. The working set is three. The target date is when the landlord says it will deliver. The outside date is when remedies start to bite. The long-stop date is when the tenant may walk. Collapsing them into a single date is common and it converts the whole remedy structure into an argument about whether the date was a promise or an estimate.

The gaps between them do the work. Target to outside is usually thirty to ninety days, and it is the window in which the tenant has protection but no leverage — a day-for-day push of rent commencement, no more. Outside to long-stop, typically another sixty to one hundred eighty days, is where escalation lives: additional free rent, sometimes two days of rent credit for each day of delay after a threshold, sometimes reimbursement of holdover or double-rent costs at the tenant’s existing premises. Past the long-stop, the tenant holds a termination right, and the terms of that right matter as much as the date: the window should stay open for at least thirty days rather than a few business days, so a tenant is not forced to choose between accepting a defective delivery and forfeiting its exit because the landlord promised to finish next week.

The single most expensive drafting decision in the whole cluster is whether rent commencement is tied to the calendar or to delivery. A lease that fixes rent commencement to a date certain while delivery floats is a lease in which the tenant can owe full rent — base rent and, depending on the wording, operating expense and tax pass-throughs as well — on a suite it cannot enter, let alone trade from. The fix is a rent commencement date defined as the later of a fixed date or actual delivery in the required condition, which has the side effect of pushing expiration by the same amount and therefore preserving the full term the tenant bargained for.

Two mechanical points get missed. Abatement should be measured on everything the tenant owes, not base rent alone; a tenant that negotiates a base-rent-only abatement in a triple-net deal still pays recoveries on a space it cannot use, and on a 14,000 SF suite those recoveries are a third of the monthly number. And abatement should accrue day for day and apply at the front of the rent-paying term, not as a one-time credit and not against the final months of the term, where a landlord can quietly recapture it in a renewal negotiation.

What an as-is clause actually waives

The baseline at common law is caveat emptor. A commercial tenant takes the premises as it finds them, and the landlord’s covenants and the tenant’s covenant to pay rent were historically independent, so a defective space was no defence to a rent claim. Only a small minority of states have moved off that baseline. Texas is the clearest, where Davidow v. Inwood North Professional Group — Phase I held in 1988 that a commercial lease carries an implied warranty of suitability — that at inception there are no latent defects in the facilities vital to the intended commercial use, and that those facilities will remain suitable. New Jersey recognised a narrower warranty against latent defects in Reste Realty Corp. v. Cooper in 1969, and later decisions have confined it rather than extended it. Elsewhere, and in particular in most of the large office and retail markets, the tenant’s protection is whatever the lease says and nothing more.

Even where the warranty exists it is fragile. In Gym-N-I Playgrounds, Inc. v. Snider, the Texas Supreme Court held in 2007 that an as-is clause paired with a general warranty disclaimer waived the implied warranty of suitability outright, and that the clause survived into the month-to-month holdover tenancy that followed the stated term. The tenant had not inspected the building at all; that made the waiver easier to enforce, not harder. The lesson is that the phrase “as is” is doing legal work even when it reads like boilerplate, and that a tenant in a Davidow jurisdiction who signs an unqualified as-is clause has given the warranty away.

Enforceability is not unconditional. The as-is clause will not shield a landlord from fraud, from a knowing misrepresentation, or from active concealment of a known defect, and the case law tests enforceability on roughly the same factors every time: whether the clause was freely negotiated, whether the transaction was arm’s length, whether the tenant was represented by counsel, whether the tenant inspected, and whether the landlord concealed something it knew. A tenant that wants to preserve a claim should keep the inspection, keep the reliance language out of the clause, and write the “as-is, except latent defects” carve-out rather than simply signing the unqualified version.

The 2025 decision in Manlius Center Road Associates, LLC v. Singh shows how narrow the escape hatch is in practice. A retail tenant discovered after signing that an interior wall it intended to demolish was load-bearing, making the removal far costlier than it had priced, and stopped paying rent. The Appellate Division held that the as-is clause barred the claim: a load-bearing wall is not a defect, it is a condition that affects renovation cost, and there was no evidence it was unsafe or contrary to code. Mistake, fraudulent inducement and frustration of purpose all failed, in significant part because the landlord had disclosed the as-is condition and offered inspection. Cost surprise is not a defect, and “as is” is what allocates cost surprise to the tenant.

What as-is does not wipe out: code, ADA and the landlord’s own work

An as-is clause removes the landlord’s obligation to improve the space. It does not erase obligations the landlord has written into the lease elsewhere, and it does not repeal public law. Three things survive it, and the drafting has to handle each one separately.

The first is the delivery conditions themselves. A lease can say “as-is” and still require the landlord to deliver the premises professionally cleaned, watertight, with all building systems serving the space in good operating condition, with landlord work substantially complete, and with all permits and a certificate of occupancy issued so the tenant can occupy immediately. That combination is not contradictory; it is the standard tenant compromise, and it is the difference between a shell and a shell you can start work in on Monday.

The second is compliance with law at delivery. The ABA’s drafting guidance is explicit that even where delivery is as-is, the premises and building should be in compliance with all laws as of commencement, including accessibility and environmental law, with systems in good working order. The trap is the other clause in the same lease: a blanket covenant that the tenant shall comply with all laws. Read literally and pushed hard, that covenant converts pre-existing building-code and accessibility violations into the tenant’s bill, and it does so invisibly, because the tenant prices its build-out from the space it walked, not from the violations it did not commission. Courts have resisted the widest version of that reading — in Botosan, a covenant to keep the premises in compliance with all laws was held not to have shifted structural access obligations, and the court observed that even a lease allocating all responsibility to the tenant would not insulate the landlord from liability under the ADA. But resistance in litigation is not a substitute for a sentence in the lease. The tenant’s ask is that its compliance obligation be limited to laws triggered by its particular use and its own alterations, with pre-existing violations expressly the landlord’s.

The third is accessibility, which deserves its own paragraph because it has a statutory cost mechanic that no lease can repeal. Both the landlord and the tenant can be liable under the ADA, and an allocation between them binds only those two parties — a disabled plaintiff can pursue either. Where a tenant alters an area containing a primary function, the alteration triggers an obligation to make the path of travel to that area accessible, and 28 CFR 36.403(f)(1) deems the cost disproportionate — and therefore not required — once it exceeds 20% of the cost of the alteration to the primary-function area. The same regulation, at 36.403(d), relieves the landlord of any path-of-travel obligation arising from a tenant’s alteration in landlord-controlled areas that are not themselves being altered. That protection is real, and it is exactly why the lease has to say who pays: the corridor, the restroom and the entrance are usually where the money goes, and they are usually not the tenant’s to touch without consent.

The arithmetic is unforgiving. A 14,000 SF build-out at $85 per foot costs $1,190,000, which sets a $238,000 ceiling on required path-of-travel spending. A $164,000 scope — an accessible route through the corridor, a widened entry, a reconfigured restroom — is therefore mandatory in full. The identical scope against a $600,000 build-out would be trimmed to the $120,000 cap. A tenant that accepted a cold shell, an as-is clause and a blanket compliance covenant has bought both the build-out and the path of travel, and then discovers the second number after the permit set is priced.

Inspection, punch list and deemed acceptance

Acceptance is where a tenant signs away the things it has not yet noticed. Landlord forms routinely provide that taking possession is conclusive evidence that the premises were in the required condition, subject only to punch-list items identified within a stated window — often five to thirty days — and sometimes to latent defects for a shorter period still. Written that way, the delivery conditions the tenant negotiated become unenforceable a fortnight after the keys change hands unless they were documented on the way in.

The counter-measures are procedural and cheap. A right to inspect before acceptance, with the acceptance form conditional rather than automatic. A joint walkthrough on a stated date. A written punch list, signed by both parties, with a cure deadline and an agreed consequence if an item is not cured — a stipulated holdback from the first rent payment is the most effective version, because it does not require litigation to operate. A defined latent-defect window that runs long enough to survive the tenant’s own construction, since some systems failures only appear under load. And a sentence making clear that acceptance is not a waiver of the landlord’s obligation to complete its own work, or of the tenant’s remedies for late delivery.

Two clauses quietly defeat all of that and are worth searching for by name. The first is a completion standard defined by the landlord’s own architect’s certificate, or by the landlord’s subjective satisfaction, with no objective test attached. The second is a force-majeure definition that reaches permitting, labour availability and material lead times. Delivery remedies are measured in days, and a force-majeure clause that captures the ordinary causes of construction delay means the abatement clock rarely starts: the tenant collects the theory of a remedy and none of the money. The ask is a hard outside date that force majeure extends only by a capped number of days, with permitting expressly carved out.

Worked example: 14,000 square feet and a ninety-day slip

A tenant signs a ten-year lease on 14,000 RSF at $34.00 per RSF base rent — $476,000 a year, $39,667 a month, or $1,304.11 a day — with estimated recoveries at $12.50 per RSF, another $175,000 a year or $479.45 a day. All-in occupancy cost is $651,000 a year, or $1,783.56 a day. The landlord represents delivery by 1 March. The tenant has to be out of its existing space by 31 March and has negotiated a six-month build-out.

Delivery slips. The landlord blames the permit queue and the electrical switchgear lead time, and hands over on 30 May. Under the best version of the clause the tenant negotiated, rent commencement is defined as the later of 1 March or delivery in the required condition, and the ninety days of delay abate $160,521 — $117,370 of base rent plus $43,151 of recoveries. Under the version the landlord proposed, rent commencement is fixed at 1 March, and the tenant pays that same $160,521 for a suite it cannot enter while carrying three months of double occupancy at the space it has already vacated. Same facts, same delay, $160,521 of difference, decided by one phrase in the basic lease information.

Now the condition. The space was delivered as-is with a blanket covenant that the tenant comply with all laws. The permit set reveals the suite restroom is not accessible and the path of travel from the building entrance does not meet current standards. The restroom rebuild prices at $38,000 and the path-of-travel scope at $164,000, both of which fall on the tenant under the as-is plus compliance-covenant combination — the path-of-travel work being required in full because the 20% cap on a $1,190,000 alteration is $238,000. That is $202,000 of work the tenant did not budget, on a lease worth $651,000 a year, and it is the exact exposure that a delivery clause requiring the premises and building to be code-compliant at commencement would have moved to the landlord.

The three numbers together — $160,521 of rent on an unusable suite, $202,000 of inherited compliance work, and a build-out that is running three months late into a fixed opening date — are the real cost of the delivery clause. None of them appears in the rent schedule, and all of them were decided before the tenant ever saw the space.

What to capture when abstracting a delivery condition

A delivery provision reduced to “as-is” is unreconstructable. Capture the condition, the dates and the remedies as three separate fields, because they are three separate risks:

  • ✓Delivery condition, verbatim, plus the itemised exhibit: shell label as written, systems actually included, utilities and capacity, ceiling and finish state, restroom and life-safety condition, and any incorporated work letter reference.
  • ✓Landlord work: scope, who designs and permits, the completion standard (objective substantial completion, not the landlord’s certificate), and the punch-list mechanism with its cure deadline.
  • ✓The three dates: target delivery, outside date, and long-stop, plus any notice obligations attached to each.
  • ✓Rent commencement basis: tied to delivery, tied to substantial completion, or fixed to the calendar — and whether term expiration shifts with it.
  • ✓Delay remedies: abatement rate (day-for-day, escalated, or none), whether abatement covers base rent only or all monetary obligations, the termination right and its exercise window, and any reimbursement of holdover costs.
  • ✓Force majeure scope as it applies to delivery: whether permitting, labour and material lead times are captured, and whether any cap applies to the extension.
  • ✓Compliance at delivery: whether the landlord represents code and accessibility compliance at commencement, whether a schedule of known deficiencies is attached, and how pre-existing violations are allocated.
  • ✓Tenant compliance covenant, verbatim: whether it is confined to the tenant’s use and alterations or reaches “all laws” applicable to the premises.
  • ✓Acceptance mechanics: inspection right, deemed-acceptance trigger, punch-list window and latent-defect window.
  • ✓Downstream dependencies: when the tenant improvement allowance starts to run, when the first charge rule should begin billing, and when the recovery base year is set — all of which key off the delivery date rather than the signature date.

Frequently asked questions

What does “as is” mean in a commercial lease?

It means the landlord is making no promise about the physical condition or suitability of the premises beyond whatever else the lease expressly says. It allocates the risk of defects to the tenant, and it is generally enforced: a Texas tenant that signed an as-is clause with a general warranty disclaimer was held to have waived the state’s implied warranty of suitability, and a 2025 New York appellate decision held that a load-bearing wall behind planned demolition work was a cost condition rather than a defect, leaving the as-is clause to bar the tenant’s mistake and frustration claims. The exceptions are fraud, knowing misrepresentation and active concealment — and in most states there is no implied warranty to fall back on in the first place.

Is a landlord required to deliver premises that comply with building code or the ADA?

Not unless the lease says so, and it usually has to say so explicitly. Both landlords and tenants can be liable under the ADA, and an allocation in a lease binds only those two parties — a plaintiff can pursue either. For alterations to an area containing a primary function, the tenant’s work triggers a path-of-travel obligation capped at 20% of the alteration cost under 28 CFR 36.403(f)(1), and 36.403(d) relieves the landlord of path-of-travel duties arising from tenant alterations in landlord-controlled areas that are not themselves being altered. That is precisely why the lease must state whether the landlord warrants compliance at commencement and who funds path-of-travel work in common areas.

What happens if the landlord delivers late?

Whatever the lease says, which is why the clause needs three dates rather than one. The ordinary ladder is day-for-day abatement of rent for the delay window, escalated credit — sometimes two days for each day of delay — after an outside date, reimbursement of holdover or double-rent costs at the tenant’s existing premises, and a termination right after a long-stop date with the deposit returned. The remedy that matters most is whether rent commencement is tied to delivery at all: if it is fixed to the calendar, the tenant can owe rent on a space it cannot occupy and every other remedy is decoration.

What is the difference between a cold dark shell and a vanilla box?

A cold dark shell is structure, envelope and roof with service points at the edge and nothing distributed inside — the tenant builds everything. A vanilla box or white box has distributed core systems and basic finishes: a ceiling grid, lighting, HVAC distribution, branch circuits, primed demising walls and a code-compliant restroom, leaving the tenant to add partitions and finishes. Warm shell and grey shell sit between them, but the labels are not standardised — the ABA has noted that these construction terms have no fixed definitions — so the exhibit has to itemise what is included rather than rely on the name.

Does taking possession waive my right to complain about the condition?

It often does, or narrows it sharply. Many forms treat acceptance of possession as conclusive evidence the premises met the required condition, subject only to punch-list items identified within a set window and sometimes a shorter latent-defect window. Protect it procedurally: a right to inspect before accepting, a joint walkthrough, a signed punch list with a cure deadline and a stipulated holdback if items are not cured, and a latent-defect period long enough to survive the tenant’s own construction. Acceptance should also be expressed not to waive the landlord’s work obligations or the late-delivery remedies.

Abstracting leases with delivery condition terms?

Our specialists capture this clause — and every other one — with page citations and human QA sign-off. See Lease Abstraction for Due Diligence.

Get a quote — and a free sample round

Send one representative lease and we return the finished abstract, so you can judge the quality on your own documents before committing to anything.